About

Gold Recovery Plant Site Under Construction

Gold Recovery Plant Site Under Construction

 
 

2017 Construction Underway

The project is divided into two sites and construction is underway at both: Mine and Plant.  The Mine Site activities involve re-entering the existing Enserch Adit which will be enlarged to allow larger mechanized equipment. At the end of the current adit a new 15% incline is being driven up to the Coleman ore reserve area. This activity is expected to take about 8 months.  Mine equipment, supplies and manpower are being organized.

The Plant Site is private land under a major electrical power line. The two-story plant building is 160 feet long x 120 feet wide with a 35 foot eave hight.  The foundation work is currently underway and a concrete slab is expected to be poured in the next several weeks.  The pre-fab metal building is being manufactured and is expected to be shipped to the plant site by mid July.